Fly ash, lime sand and gypsum are manually fed into a pan mixer where water is added in the required proportion for intimate mixing. The proportion of the raw material is generally in the ratio 60-80% of fly ash 10-20% lime, 10% Gypsum and 10% sand, depending upon the quality of raw materials.

After mixing, the mixture is shifted to the hydraulic/mechanical presses. The bricks are carried on wooden pellets to the open area where they are dried and water cured for 21 days. The bricks are tested and sorted before dispatch.